Sunday, October 21, 2012

UBAC Duplex Construction Begins in September



(Aug. 2012)  3 of 4 containers making up the base of the duplex

Now that the Hostel is complete, the next part of the project is a duplex for Covenant or Free Church staff of RFIS.  The plans were also made by Mark Post at Post Associates (and member of our home church in Grand Rapids).  Ron made some modifications -- like changing it to metric measurements, and adding a lower level of 4 shipping containers for storage.  There is space between the containers for laundry, workshop, or whatever the duplex residents choose.



So in September, regardless of the fact that we didn't yet have all 4 containers which make up the lower level, construction began.  Here's what it looked like then.
(August 2012) Future site of the staff duplex (as seen from a gate in the wall to RFIS

Retaining wall behind, veranda before, floor above.  At the bottom of the picture there is space for the 4th container.
The workers are preparing the floor to be poured above the top of the containers.  They are also making shelves to go inside the storage containers. 

We are praying that the 4th container will be delivered soon   We have paid for 2 since January 2012.  Lacking those, we paid for a 3rd one which we're also waiting for.  The problem is transport.  Pray that ONE of the 3 paid for will arrive so the floor can be poured.

View of the back of the hostel (as seen from just up from the duplex.